Australia Declares Arafura-Class Patrol Vessel ‘Undertaking of Concern’

The Australian authorities has labeled its Arafura-class offshore patrol vessels (OPV) a “protection mission of concern” following supply and sustainment help delays.

The ships have been supposed to switch the Royal Australian Navy’s Armidale-class patrol boats, however quite a few delays starting in 2021 have hampered the transition.

Canberra has ordered 12 Arafura OPVs, with the primary vessel initially scheduled to enter service in 2022. Nevertheless, the timeline was unmet. The developer, Luerssen Australia, launched the ship in December 2021 attributable to unspecified delays.

As of this month, the patrol boat has but to bear sea trials with the Australian Navy, placing the deliberate 2024 commissioning in jeopardy.

The Australian Defence Division assured that the nation and the contractor are working collectively to develop a remediation plan for the troubled OPVs.

‘Ailing-Geared up’ for Australia

Australia’s Arafura-class vessel is 80 meters (262 ft) lengthy and has a complete displacement of 1,700 tons.

Ezoic

It has three 8-meter (26-feet) sea boats, state-of-the-art sensors, and command and communications methods to successfully fulfill constabulary and maritime patrol missions.

Nevertheless, the mission was held up attributable to manufacturing and weapons integration points.

The primary vessel within the class was launched with no fundamental gun after a contract with Leonardo to supply 40-millimeter weapons was canceled attributable to issues with technical certification.

Ezoic

Moreover, the unclear commissioning date has reportedly made some officers within the protection division assume that the ship is ill-equipped for the challenges dealing with Australia.

Preliminary Treatment

In 2022, the Australian authorities awarded a contract to Austal to ship six Advanced Cape-class patrol boats to the Royal Australian Navy.

The transfer was meant to cut back the chance related to the transition from Armidale to Arafura.

In simply over 18 months, the producer delivered all vessels beneath order.

It nonetheless must be decided if the Advanced Cape-class boats will change the Arafura ships. Nevertheless, Canberra ordered two extra Advanced Capes final 12 months, bringing the fleet to eight.